Modified Schooner Completed In Monroe |
|
|
 |
Day 6
First floor timbers and midfloor installed.
|
 |
Day 7
Prow post and second floor walls are up.
|
 |
Day 9
Roof system and sheathing installed.
|
 |
Day 14
Dormers sided, soffits and fascia installed.
|
 |
Day 30
Doors and windows installed. Prow siding completed.
|
| |
|
A 2,400 sf modified Schooner was delivered to Monroe, WA. Builders arrived the same day and installed the mudsill onto the perimeter concrete foundation.
The homeowners selected our laminated cedar timbers (Phoenix System) as their wall system. This home has a "prow front" Great Room / Kitchen / Dining area.
This home was project managed by a mother / daughter team.
|